Skip to main content

Goodwood, Springbank and Daws Road Intersection Upgrade

About the project

Goodwood Road is one of southern Adelaide’s major north-south arterial routes, with Springbank Road and Daws Road providing a key east-west connection.

On average more than 60,000 vehicles a day travel through this location, with travel time delays in peak periods.

There have been 35 crashes in the past five years, including 14 casualty crashes.

The Department for Infrastructure and Transport (DIT) will be upgrading the intersections of Springbank, Daws and Goodwood Roads to improve safety and travel times for motorists.

Once complete, the upgrade will improve connectivity, capacity and safety for all users.

Prior to finalising the current design, the department investigated multiple options for this intersection. Following community feedback, new data and detailed costings, a realigned four-way intersection will be delivered.

The $61 million project is jointly funded (50:50) by the Australian and South Australian governments. Major construction works for the intersection upgrade commenced in late January 2021, with project completion expected in late 2021, weather permitting.

The successful tenderer for the major works contract on the Goodwood, Springbank and Daws Road Intersection Upgrade is BMD Constructions.

The current proposed treatments for the new four-way intersection are:

  • Road widening on Goodwood Road to provide three through lanes southbound and a left turn onto Springbank Road.
  • Road widening on Goodwood Road to provide dual right turn lanes onto Daws Road.
  • Road realignment on Daws Road to provide two through lanes onto Springbank Road, and a left turn onto Goodwood Road (northbound).
  • Road realignment on Daws Road to provide dual right turn lanes onto Goodwood road (southbound).
  • Road realignment on Springbank Road to provide two through lanes onto Daws Road, and dual right turn lanes onto Goodwood road (northbound).
  • Road realignment on Springbank Road to provide dual controlled left turn lanes onto Goodwood Road (southbound).
  • Extension of dual right turn lanes from Goodwood Road onto Springbank Road.
  • Road widening on Goodwood Road to allow for an additional through lane northbound, and a left turn onto Daws Road.
  • Upgraded pedestrian crossings within the intersection, including new pedestrian crossing and lights.
  • New and upgraded pedestrian ramps and footpaths around the intersection.
  • New and upgraded traffic signals and road lighting.
  • Dedicated bicycle lanes on the approaches and through the intersection.
  • New kerb and gutter where road realignment and widening is occurring.

Please note, this is an artist's impression for illustrative purposes only and not a final design. Please click here to download this current plan.

DIT COVID-19 Response

The Department will continue to tailor community engagement opportunities in line with the latest COVID-19 advice from health authorities.

Face-to-face engagement opportunities may be restricted and we will continue to be guided by the advice of health authorities, with the health and safety of our stakeholders always our highest priority.

Engagement with community and industry is crucial and we will facilitate information sessions as much as possible to enable face to face engagement.  It is important to assist in managing these events that you register as requested to enable physical distancing as much as possible.

Community Engagement

Early engagement and community feedback

As part of the project’s early concept design and review process, DIT held two information sessions to meet members of the community and seek feedback.

The information sessions were held at the Colonel Light Gardens RSL on Wednesday 23 October 2019, between 5.30pm and 7.30pm and Saturday 26 October 2019, between 1.00pm and 3.00pm.

In addition to the information sessions, the community were invited to provide their feedback via the YourSAy platform. This consultation commenced on Wednesday 30 October 2019, and concluded on 29 November 2019.

All feedback received from the community was reviewed and considered by the project team and as a result the concept design has been updated to include:

  • Left turn slip lane from Springbank Road onto Oxford Circus;
  • Left turn slip lane from Daws Road onto Springbank Secondary College car park;
  • Left turn slip lanes on Goodwood Road and Daws Road updated to remove control and improve efficiency;
  • Upgrade of the existing ‘Koala’ crossing on Daws Road to a pedestrian actuated (push button) crossing (PAC);
  • Define the border of Oxford Circus Reserve and the new road reserve on Springbank Road to retain heritage value of Colonel Light Gardens; and
  • U-turn facility on Daws Road to assist with accessing the Springbank Secondary College.

Receiving feedback from the community is important and will continue to help inform the development of the design, with early works commencing in March 2020, and major construction expected to commence late 2020. Project completion is expected by the end of 2021, weather permitting.

What’s next?

Pavement day/night works

Works to install new pavement along Goodwood Road, Springbank Road and Daws Road to facilitate the new four-way intersection, will be undertaken throughout the day and night during the April 2021, school holidays while traffic volumes are lower. This allows works to be completed in a shorter timeframe, minimising the duration of construction impacts to traffic and the surrounding community.

Night works, traffic restrictions and weekend intersection closures will occur from 7pm Friday, 9 April 2021, until late April 2021, with limited access to Goodwood Road from Springbank Road and Daws Road.

During this time, a number of traffic switches will be implemented. Please see maps and additional details in the latest notification for traffic restrictions.

Please plan ahead and allow extra travel time, take extra care when workers are on site, and observe speed and lane restrictions, traffic controllers and signage when travelling through the area.

For further information please download the notification

Stormwater night works

Night works involving the installation of new stormwater infrastructure for the Goodwood, Springbank and Daws Road Intersection Upgrade Project commenced on 16 March 2021, and continue through to late April, 2021.

While the majority of works are being undertaken during the day, night works are also required. To minimise the impact to road users and ensure the works can be completed safely and efficiently, works will be undertaken at night between 6pm and 6am, Sunday to Friday. No works will be undertaken on Saturday night.

Further night works will be required during major construction. Advance notice of the night works will be provided as works progress.

For further information please download the notification

Major construction on the intersection upgrade commenced in February 2021, with project completion expected by the end of 2021, weather permitting.

Publications

Pavement works (day/night) - April 2021

Night works - March 2021

Construction Update - February 2021

Night works Notification - October 2020

Night works Notification - August to September 2020

Community Information Session - July 2020

Early Service Relocation Works Notification - June 2020

Property Demolitions and Site Assessments Notification - March 2020

Property Demolitions Fact Sheet - March 2020

Invitation to Community Information Drop In Session - February 2020

Project update and early site investigation works notification

Invitation to Community Info Session and project update

Proposed treatments plan

Media Releases

New fix to remove Springbank dog leg - 6 May 2019

For further information

If you have any further enquiries or would like to register your interest in the project, please visit the Registration, Feedback and Suggestions page, email dit.communityrelations@sa.gov.au or telephone 1300 765 699.