About the project

We are improving safety and connectivity for pedestrians and cyclists on Kings Road in Salisbury Downs.

We are delivering a new Bicycle and Pedestrian Actuated (push button) Crossing (BPAC) on Kings Road and a new Shared Use Path between Kings Road and York Terrace, adjacent to the Gawler railway corridor in Salisbury Downs.

    What's happening

    To minimise impacts to the community, works will be undertaken in two stages.

    Bicycle and Pedestrian Actuated (push button) Crossing

    Works will commence on the new BPAC in late 2025, with completion expected in early 2026. Advance notice will be provided before any works commence.

    The existing pedestrian signals (150 metres west of the rail crossing) will be removed as part of these works but will not be decommissioned until the new BPAC is active.

    Shared Use Path

    We are currently working through the detailed design and will provide more information as the project progresses. Construction is expected to commence once the new BPAC has been completed with overall project completion expected in mid-2026.

    Fast facts

    Status

    Planning underway.

    Location

    Kings Road, Salisbury Downs.

    Funding

    Part of the South Australian Greenways and Cycle Paths Program.

    Timeline

    Construction underway

    Late 2025
    Works on the new BPAC commence.

    Open to public

    Early 2026
    New BPAC in operation.

    Construction underway

    Early 2026
    Construction of the new shared use path commences.

    Open to traffic

    Mid 2026
    Both stages of the project complete.

    Subscribe to project updates





    By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy.
    You may unsubscribe at any time.

    Contact

    Engagement Team

    Explore the project