Schedule

Below is a table of the estimated timing of major milestones for the Belair Line Renewal Project.

Activity  Timing
Successful contractor selected February 2009
Contract awarded to John Holland Rail and Coleman Rail to design and construct the Belair Line Renewal March 2009 
Start major construction works (Belair line closed) Sunday, 26 April 2009
Complete first stage of track upgrade (Belair Line reopened) Sunday, 23 August 2009

 

Belair line