Schedule

Below is a table of the estimated timing of major milestones for the Belair Line Renewal Project.

Activity Timing
Successful contractor selectedFebruary 2009
Contract awarded to John Holland Rail and Coleman Rail to design and construct the Belair Line RenewalMarch 2009
Start major construction works (Belair line closed)Sunday, 26 April 2009
Complete first stage of track upgrade (Belair Line reopened)Sunday, 23 August 2009